Deliverable Progress Measurement
As a guideline for progress assessment and to determine percent complete for deliverables prepared in the course of a home office engineering project, the users should apply the milestone tables as agreed upon by the Project Team. The progress ranges shown for each type of document / deliverable executed are representative of the work required to complete the deliverable. These should be reviewed and adjusted to suit the varied circumstances inherent in each project. Any change to these guidelines should be reviewed by the engineering department manager responsible for that particular deliverable prior to their use on the project.
The ranges for progress measurement determined by the milestone pattern represent the specific scope of work to be performed within that deliverable's budget. The length of the project and the duration of its activities would affect the way progress is assessed as well as the timing of the update cycle required for each project weekly, biweekly, or monthly. The reporting frequency should be established early in the project.